Home Bangladesh Aminbazar-Gopalganj transmission line comes into operation after 2-yrs
Bangladesh - District - December 17, 2022

Aminbazar-Gopalganj transmission line comes into operation after 2-yrs

Staff Correspondent: After more than two years delay, the Aminbazar-Gopalganj 400KV power transmission line came into operation crossing the Padma River.
“The line was commissioned successfully at 1:40pm on Thursday (15 December) from Gopalganj grid substation with 400KV voltage”, the Power Grid Company of Bangladesh (PGCB) said in a Facebook post.
However, PGCB managing director Golam Kibria said that although the line was commissioned, electricity flow will not be given through this line.
“We’ve planned to flow electricity from next Saturday on test basis and then step by step it will be fully commissioned by gradually synchronising with all the systems”, he told UNB.
PGCB officials said that the full commissioning of the newly constructed line will facilitate electricity transmission from the two large power plants – 1.320 MW Payra and 1,320 MW Rampal power plants – in the country’s southern region to Dhaka city.
Of these, the Payra power plant having two units, each 620 MW capacity, set up in joint venture with Chinese company, have already been commissioned. The first unit (620 MW capacity) of Rampal power plant is also being built in joint venture with an Indian company and it is expected to be commercially commissioned in March next year.
“If the electricity from these two plants can come to the capital city, it will play an important role to improve the power supply situation”, said a top official of the Power Division.
The government had undertaken the implementation of the Aminbazar-Gopalganj transmission line in 2016.
But due to construction of the Padma Bridge, works of tower installation in Padma River remained suspended until completion of the bridge construction. As a result, the project experienced a huge delay to complete.
The PGCB in the Facebook post mentioned that the newly constructed Aminbazar-Gopalganj 400KV power transmission line has been successfully commissioned with charging power by the PGCB.
The length of the line from Gopalganj to Aminbazar grid substation is 82.5km. Of which there is a 7.5km river crossing on Padma River.
The Gopalganj to Aminbazar line has a total of 226 towers. A total of 11 tall towers have been constructed in the Padma River and also on both sides for facilitating the river crossing.
As the line has been successfully charged at 400KV voltage, soon after all technical preparations and evaluations, power transmission (load flow) will be started on this line.
With the commissioning of the newly constructed line, the previously constructed Payra-Gopalganj 400KV line and Gopalganj-Mongla 400KV line have been connected to the Aminbazar grid substation on the outskirts of Dhaka.
This has made the connection to the national grid stronger and more reliable with the greater Khulna and Barishal regions, the PGCB mentioned.

Check Also

Dev work of 63 municipalities progresses in full swing

Staff Correspondent: The project work aimed at enhancing infrastructure development and ma…