Home Uncategorized Terminal 3 of HSIA likely to be completed by June 2023
Uncategorized - June 6, 2021

Terminal 3 of HSIA likely to be completed by June 2023

Construction progress ahead: Mahbub

Staff Correspondent: The construction work of Hazrat Shahjalal International Airport’s (HSIA) Terminal 3 is ahead of schedule, said M Mahbub Ali, State Minister for Civil Aviation and Tourism, while observing the progress of construction yesterday.
In June 2021, 14.5 percent of the work of Terminal 3 was projected to be complete. However, 17.5 percent of the work has been completed till now. The junior minister said the size of the terminal would be more than double of the current airport. The terminal will be connected to Ashkona Hajj Camp through a tunnel that will allow pilgrims to enter the airport directly from the camp.
The state minister said the terminal’s construction work did not stop for a day, even when the whole world was at a standstill due to the Covid-19 pandemic. The construction of this terminal is expected to be completed in June 2023. However, there is hope the work will finish ahead of schedule.
“Metrorail will be connected to the third terminal of the airport. A separate station will also be built. Through this, the passengers coming to Bangladesh will be able to go to their destinations by metro rail. Anyone will be able to go directly to the departure area of the airport from any station in Dhaka by metro rail,” Mahbub also said.
Secretary to Civil Aviation Ministry Mokammel Hossain; Chairman of Civil Aviation Authority of Bangladesh Air Vice Marshal M Mafidur Rahman; Managing Director and Chief Executive Officer of Biman Bangladesh Airlines Dr Abu Saleh Md Mostafa Kamal and other senior officials were present. Prime Minister Sheikh Hasina, in December 2019, inaugurated the construction work of the new terminal, which is expected to be modern, world-class, and more befitting of an aspiring higher middle-income country.
The three-storied terminal building, covering an area of 2.30 lakh square metres, will be built by Mitsubishi and Fujita of Japan, and Samsung of South Korea.
It will have 115 check-in counters, 64 departure and arrival immigration desks, 27 baggage scanning machines, 40 scanning machines, 12 boarding bridges, 16 carousels, and 11 body scanners.
There will also be a new car parking facility for 1,230 vehicles, a new 63,000 square metre import and export cargo complex, a 5.42 lakh square metre apron for 37 aircraft, among others.
A water supply system, sewerage treatment plant, intake power plant distribution system, equipment of cargo complex, airfield ground lighting system, and hydrant fuel system are also included in the project, according to civil aviation ministry officials.
Around two crore passengers will be able to use the airport following Terminal 3’s construction, 70 percent of the funding for which is coming from the Japan International Cooperation Agency (JICA).
In its current form, Hazrat Shahjalal International Airport can handle eight million passengers a year. But the number of passengers is expected to reach 14 million by 2025 and 24.8 million by 2035.

Check Also

Majority of share market investors lose capital

-Facing confidence crisis-Market lost Tk 76,000cr-Index lost 500 points Mahfuja Mukul: The…